Transport and Traffic Planners (TTPI) Inc.
Transport and Traffic Planners (TTPI) Inc.
Duration: November 2020 – January 2021
Client: CTI Eng’g. International Co., Ltd.
Traffic Survey under the Preparatory Survey for Central Mindanao High Standard Highway Construction Project (Cagayan de Oro – Malaybalay Section)
The survey is aimed to determine the current traffic situation in the study area in terms of vehicular volume, road space and travel speed. Conducted manufacturing and logistics’ company interviews in the study area.
Duration: January 2020 - March 2021
Client: Land Transportation Franchising and Regulatory Board (LTFRB)/Department of Transportation (DOTr)
The project aims to achieve the following:
Duration: July 2019 – September 2019
Client: ARUP of Hongkong
Feasibility Study for Laguna Lakeshore Road Network: Vehicular Survey at Surrounding Area of Laguna Lake
Collect the baseline vehicular traffic flow information along the surrounding roads in Laguna Lake area.
Duration: May 2019 – September 2019
Client: CTI Engineering International Co., Ltd. (CTII), Japan
Traffic Survey in Luzon
Under the Study of Masterplan on High Standard Highway Network Development, Phase 2
TTPI was subcontracted by CTII of Japan to undertake the Luzon Island wide comprehensive transport data gathering for the proposed JICA Study of Masterplan on High Standard Highway Network Development, Phase 2. The surveys conducted are:
Duration: March 2018 - June 2018
Client: DEMCOR-CEDCO JV for DPWH
Traffic Forecasts for the Preliminary Detailed Engineering and Evaluation of Improvement Along Intersections of National Primary Roads in Cebu City, Including the Cities of Talisay, Mandaue and Lapulapu.
The objectives of the study are:
Duration: October 2017 - November 2017
Client: Almec Corporation for JICA
Public Transport Terminal Survey for the Master Plan Study and Institutional Development on Urban Transport System in Metro Cebu
The Public Transport Terminal Survey aims to survey the frequency of PUJ and bus service and abstract of the terminals including location, operation system and operation hours.
Duration: August 2017 - October 2017
Client: Almec Corporation for JICA
Screen Line Survey for the Master Plan Study and Institutional Development on Urban Transport System in Metro Cebu
The Screen Line Survey aims to provide vehicular and passenger traffic information to calibrate the current distributed traffic volume obtained from the HIS. In order to obtain the required data, two surveys, namely the traffic count survey and the vehicle occupancy survey, are conducted at road sections crossing the screen lines in the Study area.
Duration: May 2017 - July 2017
Client: Almec Corporation for JICA
Cordon Line Surveys for the Follow-Up Survey on Roadmap for Transport Infrastructure Development for Metro Manila and Its Surrounding Areas
These surveys aim to determine the trips to/from the survey area made by residents living outside the survey area and to calibrate the distributed traffic volume obtained from existing database. In order to obtain such data/information, roadside origin–destination (OD) interview survey, traffic count survey, and vehicle occupancy survey are conducted on the boundaries of the survey area.
Duration: March 2017 - May 2017
Client: Almec Corporation
Traffic Count and Roadside OD Interview Surveys for the Davao City Infrastructure Development Plan and Capacity Building Project
The objectives of the survey are: to develop an urban infrastructure development plan for Davao City with a priority project list, which will ultimately improve the city’s competitiveness, safety from disasters, and general urban conditions of Davao City and to support the planning and implementation of infrastructure development effectively and efficiently through the capacity enhancement of NEDA and the City Government of Davao.
Duration: March 2017 - May 2017
Client: Almec Corporation
Household Interview Survey and Public Transport Passenger Interview Survey for the Davao City Infrastructure Development Plan and Capacity Building Project
The objectives of the survey are: to develop an urban infrastructure development plan for Davao City with a priority project list, which will ultimately improve the city’s competitiveness, safety from disasters, and general urban conditions of Davao City and to support the planning and implementation of infrastructure development effectively and efficiently through the capacity enhancement of NEDA and the City Government of Davao.
Duration: October 2014 – November 15, 2014
Client: CTI Eng’g. International
Traffic Count Surveys for Metro Manila Priority Bridge Seismic Improvement
Project (MMPBSIP)
TTPI have been commissioned by CTI Eng’g. Intl. Ltd. to undertake the transport and traffic surveys for the proposed JICA-Metro Manila Priority Bridge Seismic Improvement
Project (MMPBSIP). The objective of the survey is to know the existing vehicular volume that crosses the Pasig River. The transport and traffic surveys are part of a transport data collection activity of the study which will be used in the design of new bridge.
Duration: January 2014 - April 2014
Client: Japan International Cooperation Agency (JICA)
Lead Firm: ALMEC Corporation
Travel Speed Survey for the Roadmap Study for Sustainable Urban Development in Metro Cebu
TTPI was subcontracted by ALMEC Corporation (main consultant) of JICA in connection with the Travel Speed Survey for the Roadmap Study for Sustainable Urban Development in Metro Cebu. The survey aims to obtain driving data of taxis to provide an easier way to identify bottlenecks in the urban road network by the day and the time period.
The Survey’s results will also be analyzed to evaluate operation efficiencies, or turnover ratios, of taxis to think of demand-supply balance in Metro Cebu